Hello
this question sometimes baffles me, now if you had a ring final in 2.5 and wanted to spur of that to a light that will be switched via a fused spur, i know that on the load side of the spur it can be 1.5 but does it still have to be 2.5 from the socket to the spur as im comng straight off the socket
the same applies if i was running an extractor from the ring final its 1.5 from the load side but from the ring direct is it 2.5 as its the same loading etc
many thanks
this question sometimes baffles me, now if you had a ring final in 2.5 and wanted to spur of that to a light that will be switched via a fused spur, i know that on the load side of the spur it can be 1.5 but does it still have to be 2.5 from the socket to the spur as im comng straight off the socket
the same applies if i was running an extractor from the ring final its 1.5 from the load side but from the ring direct is it 2.5 as its the same loading etc
many thanks