I've just been asked to carry out a CU replacement for a customer and I plan to use this job to get me registered within Part P etc so I want to do everything properly, i.e notify building control.
Firstly how do I notify the building control; call them, write a letter?
How much notice before you start a job do I need to inform building control?
If during the testing of the house (I assume periodic here) I find sections are not up to current BS7671 standards is it my responsability to correct or is it just like a periodic where I inform the customer?
How much does it cost- you may not be able to answer this.
Obviously I would need to ensure the Gas and Main Water is bonded during the works etc
Firstly how do I notify the building control; call them, write a letter?
How much notice before you start a job do I need to inform building control?
If during the testing of the house (I assume periodic here) I find sections are not up to current BS7671 standards is it my responsability to correct or is it just like a periodic where I inform the customer?
How much does it cost- you may not be able to answer this.
Obviously I would need to ensure the Gas and Main Water is bonded during the works etc