Car port project currently under construction attached to side of house, 8.5m long x 3.6m wide span. 7 degree roof pitch. Joists @ 600 ctrs. As I am going with 110 x 18 t&g boards with EPDM over I believe that noggins are not required. Thoughts ?
 
Sponsored Links
I'd put them at 1/3 spans for this. They will need to be under the board joints in any case.
 
Sponsored Links
Thanks for replies. This is the look I am after hence the T&G board. More work obviously but happy to do so.
Boards are 119 x 19 x 4.2m treated. Joints will be on joists.
Just thought that with each T&G board nailed twice to each joist at 600mm ctrs that noggins would not be needed.
 

Attachments

  • Annotation 2020-05-31 134038.jpg
    Annotation 2020-05-31 134038.jpg
    82.1 KB · Views: 208
1 row of noggins down the middle done and dusted this afternoon. Makes some difference to the stability of the joists. Thanks for replies.
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top