The current DPC on my house sits a brick below FFL. When extending should I continue the DPC at the same level?The ground level outside is flat and 220mm below DPC.
If so, when I pour my floor slab and lap the DPM into the internal leaf, that will be a brick higher than the DPC....
What's the right way to do this?
If so, when I pour my floor slab and lap the DPM into the internal leaf, that will be a brick higher than the DPC....
What's the right way to do this?