I'm having a dispute with my local aggregate supplier.
I ordered 10 tonne of all in ballast to mix my own concrete for a foundation.
I started mixing one section of foundation this required 3m3 of concrete yet I have used all 10 tonne that was delivered.
I worked out it would only require between 5 to 6 tonne as each M3 should need 1.76 tonne of ballast.
However the company are disputing supplying an underweight load and saying now that it takes 2.4 tonne of ballast to make one m3 of concrete.
But this still does not make sense as this would still not mean their 10 tonnes would have all been used in trench only needing 3m3 concrete I would have only used 7.2 tons.
I've only written this quickly so if you need more info please ask me.
Thanks,
Poe
I ordered 10 tonne of all in ballast to mix my own concrete for a foundation.
I started mixing one section of foundation this required 3m3 of concrete yet I have used all 10 tonne that was delivered.
I worked out it would only require between 5 to 6 tonne as each M3 should need 1.76 tonne of ballast.
However the company are disputing supplying an underweight load and saying now that it takes 2.4 tonne of ballast to make one m3 of concrete.
But this still does not make sense as this would still not mean their 10 tonnes would have all been used in trench only needing 3m3 concrete I would have only used 7.2 tons.
I've only written this quickly so if you need more info please ask me.
Thanks,
Poe