Follow along with the video below to see how to install our site as a web app on your home screen.
Note: This feature may not be available in some browsers.
Looking for a smarter way to manage your heating this winter? We’ve been testing the new Aqara Radiator Thermostat W600 to see how quiet, accurate and easy it is to use around the home. Click here read our review.
My neighbour signed the party wall act document with regards to my loft conversion about 18 months ago. Is it still valid or would I need to have another one signed?
How long in advance do I have to serve the notice
At least two months before the planned starting date for work to the party wall.
The Adjoining Owner may agree to allow works to start earlier but is not obliged to
even when agreement on the works is reached. The notice is only valid for a year,
so do not serve it too long before you wish to start
If you need to find a tradesperson to get your job done, please try our local search below,
or if you are doing it yourself you can find suppliers local to you.
Select the supplier or trade you require, enter your location to begin your search.
Please select a service and enter a location to continue...
Are you a trade or supplier? You can create your listing free at DIYnot Local