Hi guys
i have searched for this answer but am unable to find it,
i am building an extention out of blockwork above dpc and engineering bricks below dpc, my architect has detailed that my outer leaf should be laid in 1:1:6 mortar.
What does this mean, i can appreciate that the 6 is sand to 1 part cement but what is the other 1 for ???
also when digging my foundations out it details the hole should be 600x225 and 1.2 mtrs deep, once again i understand the 1.2 mtrs down and the 600 wide but what is the 225mm for ???
Cheers in advance
Stan.
i have searched for this answer but am unable to find it,
i am building an extention out of blockwork above dpc and engineering bricks below dpc, my architect has detailed that my outer leaf should be laid in 1:1:6 mortar.
What does this mean, i can appreciate that the 6 is sand to 1 part cement but what is the other 1 for ???
also when digging my foundations out it details the hole should be 600x225 and 1.2 mtrs deep, once again i understand the 1.2 mtrs down and the 600 wide but what is the 225mm for ???
Cheers in advance
Stan.