What exactly do you mean by 'signing off' and what do you expect this to achieve?and thus need signing off
All of the electrical work should result in a certificate being issued by whoever does the work, either an installation certificate for new circuit(s) or a minor works certificate for anything modified/altered.
New circuits on their own are classed as notifiable work, modifications are not. However as this is part of building a new extension it's all notifiable anyway, and Building Control have presumably already been notified of it.
That notification covers the entire project, not just selected pieces of it.