Im having an extension built on a 70s bungalow. I just had a sparky around to quote and he said everything in the extension needs doing to regs and signing off which = £££££

The extension consists of an extended kitchen, an extended bedroom, a new bedroom and a garage

Now I understand that any new circuit will trigger a need to be signed off,i understand that but I think the kitchen already being on its own circuit could stretch to 2 extra sockets for the kitchen and 2 for the new bedroom?

The extended bedroom doesn't really need any extra sockets so do i really need it all signing off? I have a fairly modern metal consumer unit with mostly separate circuits but this guy is talking about new circuits here there and everywhere but I think hes just creating work to make money for himself

After reading up, I think it's a possibility to get an EICR done after the extension is complete to give me a certificate to say the extension is all safe

This would save me a fair chunk of money I think, but is it something thats possible to do if my building inspector agrees?

Thanks
 
I think you're right to question the quote, because there are two quite different issues being mixed together here:

  1. Does the electrical work in the extension need to comply with current regulations?
  2. Does every part of the extension need a completely new electrical circuit, with all the associated costs?
The answer to the first is yes. The answer to the second is absolutely not necessarily.

There is also an important distinction between having electrical work tested and certified by an electrician and having an EICR carried out after the work is finished.

I wouldn't automatically accept the electrician's suggestion that you need new circuits everywhere without first understanding why.

1. The rules in England are actually quite favourable to your argument​

Under Part P of the Building Regulations, the following work is notifiable:

  • Installing a completely new electrical circuit.
  • Replacing the consumer unit.
  • Altering an existing circuit in a special location, such as the zones around a bath or shower.
However, adding sockets to an existing circuit outside those special locations is generally non-notifiable work.

Importantly, this includes kitchens in England. The rules changed in April 2013, so adding sockets to an existing kitchen circuit does not automatically require Building Control notification.

The Planning Portal confirms this distinction.


Planning Portal+1


Applied to your extension:

AreaPotential approach
Extended kitchenExtend the existing kitchen circuit, subject to capacity and suitability
Existing bedroom extensionRetain existing circuit and wiring where appropriate
New bedroomExtend an existing suitable socket circuit
GaragePotentially extend an existing circuit, depending on its intended use and electrical loading
So, in principle, your suggestion of adding a couple of sockets to existing circuits is perfectly reasonable.

There is no blanket requirement to install a separate circuit for every room.

2. Does everything have to be brought up to current regulations?​

This is another important point.

The government's Approved Document P makes it clear that when an existing electrical installation is extended or altered, only the new work has to meet current standards.

You don't automatically have to bring the entire 1970s bungalow electrical installation up to modern standards.

There are exceptions:

  • If the existing installation is unsafe and the new work would make that worse.
  • If the existing installation cannot safely support the additional electrical load.
  • If existing earthing, bonding or protective arrangements are inadequate for the new work.
The electrician must assess the existing installation before connecting new work to it.

But that doesn't mean a perfectly serviceable existing circuit needs ripping out simply because you're extending a room.


GOV.UK+1

3. Can you have an EICR afterwards instead?​

This is where I would be a little careful.

An EICR (Electrical Installation Condition Report) is designed to assess the condition of an existing electrical installation.

It isn't a replacement for the appropriate certification of newly installed electrical work.

There are different certificates for different jobs:

  • Electrical Installation Certificate (EIC): For new circuits and new installations.
  • Minor Electrical Installation Works Certificate (MEIWC): For additions or alterations to existing circuits that don't involve new circuits.
  • EICR: For assessing the condition of an existing installation.
The IET is quite clear about the distinction.


IET Wiring Regulations+1


So, if your electrician installs a new circuit, you can't simply avoid the appropriate certification by asking somebody else to carry out an EICR afterwards.

However, if you extend existing circuits, you may only need minor works certification for those alterations.

That could make a considerable difference to the cost.

4. What about getting Building Control to agree to your approach?​

I would absolutely speak to your Building Control inspector before committing to the electrician's proposal.

However, there's an important distinction: Building Control agreeing with your proposed arrangement doesn't remove the requirement for the correct electrical testing and certification.

If you use an electrician who isn't registered with a competent person scheme, notifiable work needs the appropriate Building Control or third-party certification route. This should be arranged before work starts.

If the work is non-notifiable, it doesn't need a separate Part P notification, although it still needs to comply with the relevant electrical safety requirements.


Planning Portal+1

5. What I'd be asking your electrician​

Before accepting the quote, I'd ask him to break down exactly what he's proposing.

In particular:

  1. Why does the extended kitchen need a new circuit if the existing kitchen circuit is suitable?
  2. Can the new bedroom sockets be supplied by extending an existing socket circuit?
  3. Can the extended bedroom retain its existing electrical installation?
  4. Does the garage genuinely need a dedicated circuit, or can it be supplied from an existing circuit?
  5. Is there anything about the existing consumer unit, RCD protection, earthing or bonding that prevents the existing circuits being extended?
Your metal consumer unit being relatively modern is encouraging, but it doesn't automatically mean the existing circuits are suitable for additional loads.

I'd also ask whether he's proposing new circuits because they're genuinely necessary from an electrical design perspective, or simply because that's his preferred way of doing the installation.

Those are two very different things.

My recommendation​

I wouldn't dismiss the electrician's advice, but equally I wouldn't agree to a substantial amount of additional electrical work without understanding the justification.

Your proposed approach is potentially perfectly legitimate:

  • Retain existing circuits where suitable.
  • Extend those circuits into the new areas where appropriate.
  • Install dedicated circuits only where the electrical design and anticipated loads justify them.
  • Have the new work properly inspected, tested and certified.
  • Obtain an EIC for new circuits and minor works certificates for appropriate alterations to existing circuits.
One final thing: I would specifically ask Building Control whether they are happy with the proposed electrical certification arrangements before the extension is completed. Don't leave this until the end.

You can find the official guidance here: Planning Portal – Electrical Building Regulations.


One thing I'd be interested to know​

When you say the consumer unit has mostly separate circuits, do you mean you have:

  • A separate ring circuit for the existing kitchen sockets?
  • A separate ring circuit for the existing bedroom sockets?
  • A separate lighting circuit?
And is the new bedroom going to be immediately adjacent to the existing bedroom?

The reason I ask is that, depending on the existing circuit layout, you could potentially extend the kitchen ring into the kitchen extension and extend an existing bedroom ring into the new bedroom without installing additional circuits.

That is where I suspect you might be able to make some worthwhile savings without compromising safety.
 
It's perfectly acceptable to extend the existing circuits which doesn't require signing off, you'll just inform the building inspector that's what you did.

Whether the existing circuits are suitable for extending is a different matter.
 
would save me a fair chunk of money I think, but is it something thats possible to do if my building inspector agrees?
That's the first step, ask him/her what certification will be required on completion. Up to them really.
 
Since the extension will be under LABC you have two options, either the LABC sign it off, and issue a completion certificate, or you use a scheme member electrician, even if the work does not technically need a completion or compliance certificate, the LABC will likely want at least a minor works certificate or an insulation certificate, and some years back when my mother had a pantry and toilet converted into a wet room, the LABC were rather insisting on a number of items, like an extractor fan, which since it had opening windows were technically not required. So you have to jump through their hoops.

Every edition of BS 7671 has something like this "The Regulations apply to the design. erection and verification of electrical installations, also additions and alterations to existing installations. Existing installations that have been installed in accordance with earlier editions of the Regulations may not comply with this edition in every respect. This does not necessarily mean that they are unsafe for continued use or require upgrading." so the new bit has to comply with latest edition, but existing may not need upgrading.

However over the years there have been alterations to the regulations to allow for plastic pipes, solar panels, EV charging, and many other items, and it says "may not" not "will not" so it is likely some parts will need up grading to allow for future use of new equipment now on the market.

Back in around 1988 I fitted RCDs to my home, not because the regulations required them, but my son had passed his RAE and I wanted to protect my family, you have to consider if you could ever forgive yourself if a family member was in the future injured because you wanted to save a few pounds.

I have all RCBO protection in my home, as I felt the chance of losing food, or more to point having bad food in a freezer because it had tripped and been reset without realising the freezer had defrosted was not worth the risk.

You must do your own risk assessment.
 
Thank you all for the advice, really helpful of you

Whats in my favour is that because an old person lived there, theres probably 2 double sockets and 2 single sockets across living room and 2 bedrooms! So extending some of them is hardly a strain on a circuit.

I'll speak to my BI first but as Herts P&D said that doesnt mean i wont also need certification

I've got another sparky coming next week to advise but he has let his testing certs go as he does that through his boss so it saves him cash but he can advise at least.

Im no electrician but im not green either, I have a feeling he wants new stuff to be safer but probably more about money

Thank you so much
 
Ps

I read that if there is currently wiring for an electric hob, i can extend it as the hob was against a wall but the new hob will be on an island so can i either extend that cable or run a new cable but it will still be classed as an old circuit as far as regs go? Thanks
 
I've got another sparky coming next week to advise but he has let his testing certs go as he does that through his boss so it saves him cash but he can advise at least.

Any qualified electrician can issue electrical certificates, such as a Electrical Installation Certificate, a Minor Electrical Installation Works Certificate (which is all you need for extending circuits) or an Electrical Installation Condition Report. What a non-registered electrician cannot do is to certify that his work complied with the Building Regulations.

Since the electrical work is not notifiable, you don't need any Building Regulations certificate for it, although I think that some LABCs can get a bit sniffy and say that non-notifiable work which is part of a larger project which does require Building Regs sign off does still need to be certified.

Easiest out is to remove the electrical work from the scope of the extension, get that built and signed off (but not plastered or decorated), then get a qualified electrician to extend the circuits and issue a MEIWC.
 

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top