Hi guys,
Just wondering what the professional technique is for the following,
An rsj is to be fitted in place of a supporting wall. The ceiling is acro'd up and the wall removed. The brickwork to support the beam is removed including space for the padstones and mortar joint below the padstone.
The rsj is acro'd into position tight to the wall plate/joists above.
Now what's the "correct" technique to raise the padstone upto the rsj and fill the mortar joint below?
I assume it requires a shim of some sort, if so should this be removed and filled when set and what should it be comprised of?
Just wondering what the professional technique is for the following,
An rsj is to be fitted in place of a supporting wall. The ceiling is acro'd up and the wall removed. The brickwork to support the beam is removed including space for the padstones and mortar joint below the padstone.
The rsj is acro'd into position tight to the wall plate/joists above.
Now what's the "correct" technique to raise the padstone upto the rsj and fill the mortar joint below?
I assume it requires a shim of some sort, if so should this be removed and filled when set and what should it be comprised of?