rewiring no regulation compliance cert. needed?

He didn't receive anything from him though. :( How strict are the councils with this certifying after work is completed malarky?
 
It is not date work was done it is the date it was planned so as long as planned before Part P came in then no need for completion certificate.

However there will still be a requirement for an installation certificate which shows that tests were carried out and results noted.
 
He didn't receive anything from him though. :(

I’m being asked for a building regulation compliance certificate by solicitors.... until today I have never heard of one of these and didn’t get anything from the electrical guy.
he meant that he didn't get a Building Regulations certificate, not that this qualified electrician contravened the Wiring Regulations by not issuing an EIC.


How strict are the councils with this certifying after work is completed malarky?
The only way to make it legit now is to apply for regularisation. That is likely to involve a PIR being carried out by the council's choice of contractor. The council could, if they wanted to be evil, insist on laying open of all cable routes.
And regularisation costs twice what the normal approval does. In total it could get near to £1,000.
 
i will be honest i didnt buy the place until 2005, sorry i said 2000 but thought the buyer might be on this forum :?

impossible to say the works started in 2004 :-( as we didnt move in until summer 2005. sorry for not making this clear but i didnt think these dates would matter when i posted.....

there was no installation certificate afterwards so i dont have this, i have nothing.
 
It is not date work was done it is the date it was planned so as long as planned before Part P came in then no need for completion certificate.
That's not so, I'm afraid. Building Regulations transitional arrangements only apply to work already submitted for approval.

And even if it were I don't think that the solicitor would be carrying out due diligence if he didn't ask for proof that it was planned, e.g. correspondence, minutes of meetings, invoices for design work, dated submissions of plans and quotes to the client etc.

Otherwise anybody who had been in a house since before 2005 could at any time say "Oh I always planned to rewire".
 
Most Council hold to a 6-12 month window from work done to point where they may take enforcement action.

Yours being 5+ years won't interest them. It will interest the potential purchasers solicitor since you have declared work done since moving in that should have building control notification and part P sign off via a scheme provider.

You now have a choice:-

Ask mate that did works to return and complete a EIC for the property and supply a copy to the solicitor.

Volunteer to have a completely neutral contractor appointed to do a periodic inspection report, and accept the cost of any remedial on that report.

Or you could commission a scheme member contractor and ask them to update the works to 17th edition. The 17th came out in July 2008 and the best "badge of cert" for the property would be 17th cert, with correct 10mm earth bonding, and a CU that works to auto discon supply (ADS) which is the requirement via 17th for domestic properties.

A PIR would be about £200, a new CU, bonding and 17th cert circa £500 *


* pure guess, based on no issues with existing wiring, easy bonding runs and a board with less than 8 circuits.
 
I think you've got two options:

1. 'fess up to the buyers. They might not care. They might accept a periodic inspection report. They might be willing to let it go in return for a reduced price.

2. Ask the council for a regularisation certificate. This will take a bit of time and it will cost you a few notes.
 
Sorry you feel that way Shed but thanks for your comments, I was just being overly paranoid and I didn’t know the dates would actually matter. As solicitors and the like are involved I was a little concerned. FYI, I think you’ve actually misquoted me there but maybe I deserve that.

If anyone still cares I think after speaking to the electrician I will go with one of the 2 options above, well I don’t have any other choice!

Cheers Chris/RossR

I just phoned the council and they there was nothing could do and suggest I get a PIR and that was it.....
 

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top