Tiling a new concrete floor

  • Thread starter Thread starter marsaday
  • Start date Start date
M

marsaday

do you have to let the concrete dry out before tiling? and if so how long. ta
 
Hi marsaday
6 weeks for new concrete to cure/dry
3 weeks for cement:sand screeds
2weeks for cement:sand render
hope this helps :D
 
thanks. any idea which adhesive to use. are they all the same fine aggregate/cement mixes. b and q do a bag for £8 odd. will this be any good with underfloor heating ?
 
for underfloor heating you need a flexible adhesive, go to a tile store for one, bal or weber do very good floor adhesives.
 