And we still don't know the size of the existing beams....(sigh).Update:
well quite a bit has happened since my last post:
1. BC were asked to inspect the steels/blockwork and commented they would not sign it off until the SE said it has been built according to his design/plans
2. We paid another SE to do some calcs for a couple of small internal beams and at the same time to give us his opinion on the big beams & blockwork. We're still waiting for his report but verbally he said those big beams/bearings/blockwork do not look right but he did not want to get involved
3. My son wrote a lengthy email to the SE the builder used, who is MICE, MISE registered (I checked and he is registered and apparently a 1-man SE Ltd Company) cc to the builder & BC, with photos and asked about steel length, bearings, padstones & blockwork. It has taken a while but he has just replied "due to confidentiality reasons he cannot answer any of the questions as the Builder is his client and not my son" and all questions must come through the builder.
4. the builder is saying he doesn't understand the questions being asked of the SE so is effectively blocking those questions being asked of the SE
5. As the SE the builder used is a member of MISE, I checked their Code of Conduct and I believe he has a duty of care to anyone involved in the build which I interpret that he should answer those questions directly my son posed - being the end user .. is that right ?
In summary, the builders SE appears to be covering for the builder using "confidentiality" as an excuse and the builder is now throwing his toys out of the pram raising other issues in an attempt to get my son to accept what has been built probably knowing what he built is wrong and is using a tactic he has used many times before.
So my question is: can we write again to the builders SE insisting he answers the questions under the MISE Code of Conduct, or risk a complaint to that body if he refuses. At some point the builders SE is going to have to cut the builder lose and chose which side to be on, my sons or the builder, or risk dealing with a MISE complaint.
Once we have his official answer, be it the build id OK or not OK then we can move forward to getting the beams resolved by the builder or by a 3rd party.
This...They're taking you for a ride.
Even if the SE answered now, would you trust his answers?
Get a new SE to do the calculations and check that bodge.
The, armed with the report go for the builder and his mates, the SE.
Report them to everyone and everything.
HSE are quite good at kicking rogue builders in the butt.
And I bet the SE would have his own trouble with his regulator.


it can get messy if say, the client supplied plans to the builder who then contracted engineering design based on those plans
I'd suggest you step aside from blame-throwing, as you'll probably never resolve anything if you're dealing with cowboys as it appears.Update:
well quite a bit has happened since my last post:
1. BC were asked to inspect the steels/blockwork and commented they would not sign it off until the SE said it has been built according to his design/plans
2. We paid another SE to do some calcs for a couple of small internal beams and at the same time to give us his opinion on the big beams & blockwork. We're still waiting for his report but verbally he said those big beams/bearings/blockwork do not look right but he did not want to get involved
3. My son wrote a lengthy email to the SE the builder used, who is MICE, MISE registered (I checked and he is registered and apparently a 1-man SE Ltd Company) cc to the builder & BC, with photos and asked about steel length, bearings, padstones & blockwork. It has taken a while but he has just replied "due to confidentiality reasons he cannot answer any of the questions as the Builder is his client and not my son" and all questions must come through the builder.
4. the builder is saying he doesn't understand the questions being asked of the SE so is effectively blocking those questions being asked of the SE
5. As the SE the builder used is a member of MISE, I checked their Code of Conduct and I believe he has a duty of care to anyone involved in the build which I interpret that he should answer those questions directly my son posed - being the end user .. is that right ?
In summary, the builders SE appears to be covering for the builder using "confidentiality" as an excuse and the builder is now throwing his toys out of the pram raising other issues in an attempt to get my son to accept what has been built probably knowing what he built is wrong and is using a tactic he has used many times before.
So my question is: can we write again to the builders SE insisting he answers the questions under the MISE Code of Conduct, or risk a complaint to that body if he refuses. At some point the builders SE is going to have to cut the builder lose and chose which side to be on, my sons or the builder, or risk dealing with a MISE complaint.
Once we have his official answer, be it the build id OK or not OK then we can move forward to getting the beams resolved by the builder or by a 3rd party.

As for payment, payment has been regularly as the project progressed, but there is still mid-teens £000's outstanding so we're not going to be paying anything until this is resolved and because the builder is being petulant, the goodwill has gone, so I'm minded not to pay anything until everything about the build is finished. It would not surprise me if he downed tools and walked off site.
I have copies of the SE calculations but I won't post them in case this matter progresses in a more formal direction. But these images show the size of the 2 large beams in the Bifold area and the double beam holding the flat roof which you can see on earlier photos.And we still don't know the size of the existing beams....(sigh).![]()
Me too. Ivor is much better at it.I'd suggest you step aside from blame-throwing
152mm x 152mm column spanning 10m!I have copies of the SE calculations but I won't post them in case this matter progresses in a more formal direction. But these images show the size of the 2 large beams in the Bifold area and the double beam holding the flat roof which you can see on earlier photos.
these images show the size of the 2 large beams in the Bifold area and the double beam holding the flat roof which you can see on earlier photos.
That drawing may be out of date as I measured that outermost beam when I was onsite as 180 x 200 and the one over the Bifolds I measured as 205 x 210 and the Double beams are 530 x 210152mm x 152mm column spanning 10m!![]()
If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.
Select the supplier or trade you require, enter your location to begin your search.
Are you a trade or supplier? You can create your listing free at DIYnot Local