Having discussed the foundation / drainage plans with my neighbour over the holiday period he seemed happy enough with the extension left hand foundation but more concerned about a left hand drain (due to proximity).
There’s no Party Wall Act (i.e. section 6(1) / 6(2) Adjacent Excavation Notice) in this jurisdiction so we'd be required to cope with a claim under common law if that were to ever arise.
I've therefore attached an updated work in progress pdf (had to chop a lot of detail from the underlying svg before it would upload) which, currently, does not include the previously suggested left hand foul run in case this might suffice.
The garden hot tub foul connection no longer exists and all future (potentially 5 of mini split) aircon indoor unit condensates' are shown draining via storm bottle gully traps. The additional IC in the alley (right patio) between the existing garage and extension right hand side also permits the ensuite WC to run along a main channel and all connectors at the foul IC's are now 45° or less.
It's, hopefully, more viable than the original plan and, on first calculation check, all fits and keeps the 450mm IC's (9 of) and single 320mm IC within regulation invert/obverts (I think).
Would appreciate any comment to hint that it could have a reasonable prospect of gaining BC approval – it’s still a bit like a picture of the LHC though, so apologies for that.
Extension oversite concrete drainage query (I hope the plan drawing makes this clearer than the following written description!!)
The reason for the additional shading / colouring along the left side of the extension and existing wall being that i'm not particularly confident of my updated extension oversite drainage scheme described below.
In summary, again, the rear/right patio FGL is above extension oversite concrete by 124mm. That oversite level is the same as the top surface of the existing (150mm thick strip ) rear (entire left-to-right) foundation.
In attempt to provide extension oversite drainage (the regulations require this to prevent pooling), to a lower level exterior finished ground level, i've:
Externally to Extension
1/ At the interface between the rear patio and path (of 1200mm width) to the left of the extension the ground level has been reduced by 170mm (i.e. existing FGL here has been reduced by a 170mm single step down).
Note - if the extension oversite concrete where to be level it would all be (170 - 124) = 46mm above the path
2/ This path continues along the left of extension at the same 170mm reduced level
until
3/ At the interface of this left path and the existing rear foundation there is a 170mm step up (across a width of 750mm portion of the full 1200mm) adjacent to the existing residence left wall. The remaining (outer) path width (450mm) is not stepped up, it remains level at 170mm below rear patio FGL
Note - the 170mm step back up is to the original, non-reduced, FGL at that point. If the step up did not occur then (170 - 124) = 46mm of the existing rear strip foundation would be exposed above ground.
4/ The remaining 450mm portion of the (reduced by 170mm) path continues level toward the front garden along the existing left wall until it intersects with the existing sloping path (whose average fall along the side of the existing wall is 5.7 eightieths)
This 450mm "channel" is bounded on both sides by sections of 90mm width concrete dwarf wall (they have a top elevation with 15mm flat and 75mm sloping). The effective width of the channel is therefore (450 – 2 x 75) = 300mm.
Internally to Extension
A/ At the inner leaf of the rear extension wall and the outer leaf of the rear existing dining room wall the extension oversite concrete is 124mm below rear patio FGL.
B/ The oversite concrete is angled down from both of these boundary locations at 1/80th toward the midline of the extension. The resultant fall is 27mm. This midline oversite is now (46 - 27) = 19mm above the level of the path to the left of the extension.
C/ A 40mm dia pipe exits the 350mm left patio wall at the extension midline. Its internal oversite invert is at 19mm above the extension left path and a 1/80th pipe fall of 4mm sees its invert at 15mm above extension left path (170mm reduced) FGL.
In summary,
(i) The extension oversite concrete drains to the extension (170mm reduced level) left path surface.
(ii) The extension left path level surface drains, via a 300mm wide level (front to back) "channel" (at 2385mm towards the front garden from the existing rear foundation) at the interface between it and the existing (5.7 eightieth fall) sloping left path.
Does that seem reasonable?
PS:
the existing dining room is a Terrazzo/Cement floor which is to be replaced with suspended wooden floor. Its oversite concrete will be at the same level as the extension oversite. The plan drawing shows a similar sloping oversite drainage solution to that described above for the extension but I do not describe that here in case of adding further confusion.