Backfilling/filling cavity

Joined
17 Apr 2015
Messages
3,011
Reaction score
537
Location
Warwickshire
Country
United Kingdom
Hi
Would anyone be able to check my logic for the next steps of getting my extension out of the ground? The foundations are now poured to 450mm below damp.
- I was planning on laying one course of blocks (to get within 225mm of dpc) then filling the cavity with lean mix concrete then running the trowel along it to slope it towards the outer skin? Then laying the rest up to dpc.
- back filling after getting to dpc I was planning on using a mix of soil and hardcore, but have heard that you shouldn't use soil, any opinions appreciated!
 
Sponsored Links
No fertile matter! Clean sulphate free hard core only.

Your cavity fill method is sound.
 
Thanks noseall
Although bco has since ok'd just using soil ?! (Gary)
Think I'll look into the risks here a bit more - any views welcome
 
Sponsored Links
Ah - I was talking about the outside. I treat the inside to be an extension of the hardcore/slab compaction etc.
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top