Can anyone clarify?
Full Planning has been granted for a small unit on a plot.
The unit has a couple of offices, a workshop, and a sales counter/reception.
I know the building regs have to be followed for disability access etc, windows, insulation etc
An architect drew up basic plans. The remit was build cost 150K, quotes to build on the architects design came back at 400K!
And it is only a 26m long timber frame building single story!
Can I:
Give the architect the boot? A=Yes
It is not that complicated its a basic timber frame building.
The only planning restrictions is protect some trees and have in the design sound proofing for workshop.
Can I put a building notice in and start building straight away and use the basic footprint granted in planning and call in the BCO to sign off each stage of construction?
Or do I need to submit further detail plans and get building reg approval before submitting the building notice?
keeping in mind this is non residential?
Many thanks all!
Full Planning has been granted for a small unit on a plot.
The unit has a couple of offices, a workshop, and a sales counter/reception.
I know the building regs have to be followed for disability access etc, windows, insulation etc
An architect drew up basic plans. The remit was build cost 150K, quotes to build on the architects design came back at 400K!
And it is only a 26m long timber frame building single story!
Can I:
Give the architect the boot? A=Yes
It is not that complicated its a basic timber frame building.
The only planning restrictions is protect some trees and have in the design sound proofing for workshop.
Can I put a building notice in and start building straight away and use the basic footprint granted in planning and call in the BCO to sign off each stage of construction?
Or do I need to submit further detail plans and get building reg approval before submitting the building notice?
keeping in mind this is non residential?
Many thanks all!