I've got a manhole where my new kitchen is going. It's where the current kitchen drains join the main soil pipe. The kitchen plumbing is moving into the extension and I'm putting in a new manhole outside the footprint. The old manhole is now not required and will be buried under the new floor
I've had a chat with BCO and he suggested putting a half section of pipe in the bottom of the manhole to make a closed pipe. What would the method be? Mortar to hold it in place then a bit of pea shingle then fill the manhole with hardcore?
I've had a chat with BCO and he suggested putting a half section of pipe in the bottom of the manhole to make a closed pipe. What would the method be? Mortar to hold it in place then a bit of pea shingle then fill the manhole with hardcore?