Setting out blockwork from foundation

On the context of a garden room, I’d be unconcerned about skipping it and just putting the insulation on the dpm on the well compacted base and liquid screeding it

If you’ve already dug out for the level, crack on; it’s not a huge expense of concrete, it’s just work shovelling 3 tons of it around. Installing a liquid screed is much more a painless exercise but remember to put a membrane on top of your insulation to contain it

-

Just noticed in the initial post you talked about block and beam; has that plan changed?
 
Hi. Thanks for your reply. It is a garden room. That is being built as a house as planning permission was required due to it having a kitchen, bathroom and mezzanine level. I was going to put in a beam and block floor but I have decided I don't want the vents.

With a beam and block floor or concrete, I still.need to figure out which blocks or bricks I need to sit a 150mm wall plate on. That's the part that is confusing me.

Cheers
 

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top