hi there
I excavated a trench( 3mx45cmdepth x30cm width ) for concrete footing lastweek.it is now half full of rainwater.Would that be a problem with just removing the water and fill it with concrete .Please advise me .Thanks
You should remove any soft and loose clay/soil from the bottom of the trench. This can be difficult if saturated and is usually better to drain the trench and leave it to dry for a day or two. Does the BI need to inspect? If so they can be a bit tetchy about the quality of the clay at the bottom of trenches.
Once you have taken out the loose material, you could put in a layer of dry lean concrete mix. But best to speak to your BCO who will have his own preferences.
If you need to find a tradesperson to get your job done, please try our local search below,
or if you are doing it yourself you can find suppliers local to you.
Select the supplier or trade you require, enter your location to begin your search.
Please select a service and enter a location to continue...
Are you a trade or supplier? You can create your listing free at DIYnot Local