Hi folks, seriously need some opinions on here as to what is going on.
I paid a builder to build a summerhouse in my garden, usual things, promised he would build it in 4 weeks, and now it has been 3 months, most of it is done, but it is all now going at a snails pace.
I have paid him his instalments he asked for, but as stupid as I was, I have now realised that there are a lot of things unfinished that should have been 100% done before paying him some money, such as finalising the electrics, leaving the garden in an absolute mess [cement, dangerous tools, old wood, rubble etc), such that my son fell over and hurt himself, roof leaking water down onto front render when it rains (despite having a gutter, fascia and soffit), also they have left the ceiling lights dangling down on their wires, plumbing and drainage--well there is none installed and a sink is needing to be installed.
Anyway, I send him a letter stating that things have to improve and that he is in breach of contract and dangerous, that very same day and since then, workers have been coming every day and completing the tasks I raised.
Fine so far...
Today he replied to me stating that he has received my letter and that his secretary who happens to be a LABC building control inspector will write back to me with a reply next week, but also that they are in contact with the local council head of building control inspector and they will reply back to me next week.
???
I do not get it, I raise issues about safety and him not completing the work , so why would he want to contact building control?? Is he trying to call my bluff??
The building is within 30m2 and is made of non combustible materials, and so according to planning portal, building control should not theoretically apply.
I paid a builder to build a summerhouse in my garden, usual things, promised he would build it in 4 weeks, and now it has been 3 months, most of it is done, but it is all now going at a snails pace.
I have paid him his instalments he asked for, but as stupid as I was, I have now realised that there are a lot of things unfinished that should have been 100% done before paying him some money, such as finalising the electrics, leaving the garden in an absolute mess [cement, dangerous tools, old wood, rubble etc), such that my son fell over and hurt himself, roof leaking water down onto front render when it rains (despite having a gutter, fascia and soffit), also they have left the ceiling lights dangling down on their wires, plumbing and drainage--well there is none installed and a sink is needing to be installed.
Anyway, I send him a letter stating that things have to improve and that he is in breach of contract and dangerous, that very same day and since then, workers have been coming every day and completing the tasks I raised.
Fine so far...
Today he replied to me stating that he has received my letter and that his secretary who happens to be a LABC building control inspector will write back to me with a reply next week, but also that they are in contact with the local council head of building control inspector and they will reply back to me next week.
???
I do not get it, I raise issues about safety and him not completing the work , so why would he want to contact building control?? Is he trying to call my bluff??
The building is within 30m2 and is made of non combustible materials, and so according to planning portal, building control should not theoretically apply.