Hi
For a porch and dinning room, we need to fill 200mm 'off' virgin sand/soil.
It was specified as 100mm of hardcore, but to reach solid bed it has taken us down to a depth of 200mm
We have a "lot of bricks" that we have broken in half, plus lots of concrete
around the same size.
The area is around 5m x 4m - this will be for Blinded Hardcore.
It will be wakerplated.
We cannot call the BCO down at the moment, so my question is;
Is half a brick size acceptable?
Any advice welcome.
Thanks, Stephen