Afternoon All,
The builder who did my building work "suggested" I use a 3rd party company for my building regs rather than the council as he said it would be a "smoother process". So went with his recommendation.
On their last visit before he left site they listed out the items which needed to be completed prior to final approval being given.
The builder completed some but but but not all items, as he said the remainder were down to me and outside of his scope for the works. He advised I had 2 years to complete the items.
(He wasn't down for the interior components - fitting new doors, smoke alarms, and an extractor in my kitchen and the old bathroom which is now a utility and has has the window blocked up.
Roll on 5 months and the 3rd party company have written to me threatening if the items aren't completed within 2 months they have no choice but transfer the issue back to my local council; at my cost.
They are citing the fact we have moved back into the house which we haven't and have advised them of on numerous occasions. They don't respond then send another email... verbally they have said they need to close my file.
Are they correct in their assertions? I have limited time to complete the items? - is this documented in the regs?
Do I need an extractor in the utility room - it will still have a toilet and basin.
There is no kitchen as yet - so no extractor for that fitted and is unlikely to get fitted within the time frame.
Many thanks for any advice.
Steve
The builder who did my building work "suggested" I use a 3rd party company for my building regs rather than the council as he said it would be a "smoother process". So went with his recommendation.
On their last visit before he left site they listed out the items which needed to be completed prior to final approval being given.
The builder completed some but but but not all items, as he said the remainder were down to me and outside of his scope for the works. He advised I had 2 years to complete the items.
(He wasn't down for the interior components - fitting new doors, smoke alarms, and an extractor in my kitchen and the old bathroom which is now a utility and has has the window blocked up.
Roll on 5 months and the 3rd party company have written to me threatening if the items aren't completed within 2 months they have no choice but transfer the issue back to my local council; at my cost.
They are citing the fact we have moved back into the house which we haven't and have advised them of on numerous occasions. They don't respond then send another email... verbally they have said they need to close my file.
Are they correct in their assertions? I have limited time to complete the items? - is this documented in the regs?
Do I need an extractor in the utility room - it will still have a toilet and basin.
There is no kitchen as yet - so no extractor for that fitted and is unlikely to get fitted within the time frame.
Many thanks for any advice.
Steve