Hi all, wonder if anyone can shed any light on this it's been bugging me and can't find any literature to find out what's the correct thing to do, recently cut out some gas pipework and rerouted it somewhere else, after pulling out the old pipework I left some going through the wall to be removed at a later date. Finished tightness test and visuals etc and customer complained smelling gas after I'd left. Just wondering if that gas pipe should have been capped at both ends, nothing was connected at either end and was completely free of any other gas pipe, anyone know the legislation on that ?