When checking an installation which has 16mm incoming tails to the 100A service fuse and the same size to the meter but 25mm tails from meter to cu, which part of the tails are we concerned about when comparing to the fuse? Cheers.
Thanks folks. So just to clarify...even though the 16mm tails between the 100A fuse and the meter seem inadequate, as long as the tails are 25mm on the consumer side of the meter, then that's my only concern. Right?
Not sure what you're getting at. I meant the cable into the property from the street.
I have had much trouble getting RCD's to hold, but it doesn't matter whether it is ancient cable or new, imperial or metric, if you have an earth fault, the RCD will go open circuit..
If you need to find a tradesperson to get your job done, please try our local search below,
or if you are doing it yourself you can find suppliers local to you.
Select the supplier or trade you require, enter your location to begin your search.
Please select a service and enter a location to continue...
Are you a trade or supplier? You can create your listing free at DIYnot Local