NYY-J or 'Tuff Sheath'

See post #2 for the best answer :whistle:

So the route in total is this:

Consumer unit behind kitchen cupboards (gland SWA into CU).

Back of kitchen units for 3-4m.

Turn 90 to go through 9" solid brick wall.

Turn 90 downwards towards the ground.

Turn 90 to go horizontal under the gate for 1m.

Turn 90 to come out tye ground and go vertical up the outhouse exterior wall.

Gland into junction box directly behind the consumer unit on the inside of the outhouse.

Take the cores through to consumer unit.

It's a lot of bends in a short distance which is what I'm worried about with SWA.
 
As I mentioned, what I would do is drill up and in at 45 degrees ish, you won't blow the brick drilling from the outside and if you're ending up behind cabinets anyway doesnt really matter if the holes a bit messy inside
 
Alternative option.

When I had my EV charger installed they put an external consumer unit on the outside wall of the house. Rather than drilling in to the house to reach the original consumer unit, could I piggyback off the external one?

The external one has been tapped directly into the meter tails with Henley blocks for its feed.
 
When I had my EV charger installed they put an external consumer unit on the outside wall of the house. Rather than drilling in to the house to reach the original consumer unit, could I piggyback off the external one?
One dogs dinner lashup extended to another one.

At this point, slinging an extension lead down the garden would be a better solution.
 
One dogs dinner lashup extended to another one.

At this point, slinging an extension lead down the garden would be a better solution.

Octopus did this. My original consumer unit and service head/meter are all in a really difficult location behind kitchen units.
 
Octopus did this.
No surprises there.

My original consumer unit and service head/meter are all in a really difficult location behind kitchen units.
So as usual, the cheap and easy option was chosen over doing things properly.
Both by Octopodes and whoever shoved the kitchen in front of electrical equipment.
 
No surprises there.


So as usual, the cheap and easy option was chosen over doing things properly.
Both by Octopodes and whoever shoved the kitchen in front of electrical equipment.

I guess so but it's an old house and the supply comes in where the pantry used to be which is now just part of the kitchen. It would cost thousands to relocate the incomer, plus it can't go easily at the side of the house because it's only a narrow side entry. The kitchen is quite small too so can't just ideally leave a chunk of wall free when cupboard space is needed.

I doubt many installations are perfect and accessible in older houses.

But anyway on my situation I have refurbished top to bottom a detached brick outhouse which I now want a supply to and to do it all nicely and properly. Modifying the kitchen is a potential future job with a potential consumer unit relocation but that can't be done now. Even when it's done they won't move all the incomer supply I don't think.

So I just have to get a feed to it from the best place given what I have.
 

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top