    1) Any idea what “bonding required before first tee” means?

    this was written on my gas safety certificate (CP-12).

    I have tried to look it up and I think it is something to do with a plumbing joint (for a radiator?). Does a plumber need to do this?

    2) radiator valve leaking. Does this mean I need a new Valve? Can I replace this myself, or do I need a plumber?

    Thank you
     
  2. Sponsored Links
  3. JohnD

    JohnD

    Joined:
    15 Nov 2005
    Messages:
    70,536
    Thanks Received:
    3,980
    Location:
    Crossgates
    Country:
    Cook Islands
    1) Main Bond (earth wire) should be fixed close to where the pipe enters the house.

    If it is after a Tee you might one day decide to cut off one leg, leaving the bonding on the redundant, disconnected bit of pipe that you've cut off.


    EC15.jpeg
     
  4. ianmcd

    ianmcd

    Joined:
    15 Aug 2010
    Messages:
    21,009
    Thanks Received:
    8,155
    Location:
    Lanarkshire
    Country:
    United Kingdom
    It means earth bonding (electrical) wouldnt bother about it if I was you, a leaking radiator valve has absolutely nothing to do with a CP-12
     