Here are some pictures of the old peak CU & of the new peak CU I replaced it with.
The Old peak CU was a 4 way metalclad MEM Memera with rewirable fuses, the circuits on the old cu were:
Cooker & DSO by cooker 30A
Sockets (Ring) 30A
Lights & Meter-cupboard Light 5A
Bathroom Heater Light & Doorbell 5A
The main reason for replacing the cu is that he wants to have an electric shower fitted soon.
The Old peak CU:
The Old cu removed:
The cooker, sockets & lights circuits are all run in metal conduits in the walls, which use the conduits as earth.
Fitting the new peak CU:
New peak CU wired up:
Labeling on the new peak CU:
Off peak CU:
Metering:
Meter Cupboard:
The Old peak CU was a 4 way metalclad MEM Memera with rewirable fuses, the circuits on the old cu were:
Cooker & DSO by cooker 30A
Sockets (Ring) 30A
Lights & Meter-cupboard Light 5A
Bathroom Heater Light & Doorbell 5A
The main reason for replacing the cu is that he wants to have an electric shower fitted soon.
The Old peak CU:
The Old cu removed:
Conduit wires
- mdbalson
- 1
Wires for:<br><br>Cooker <br>Sockets<br>&<br>Lights.<br><br>Wiring is in metal conduit with the...
The cooker, sockets & lights circuits are all run in metal conduits in the walls, which use the conduits as earth.
Fitting the new peak CU:
New peak CU wired up:
Labeling on the new peak CU:
Off peak CU:
Metering:
Meter Cupboard: