I need some advice please
We are currently experiencing problems with our attached garage conversion into a habitable room which have been on-going now for 3 months
We were advised that a Building Regulations application would be the best way to go and we submitted an application to the Local Council.
The application was accepted and a payment was made to the local council and work commenced
At the front of the house the garage door was removed and the builder dug out the foundations and called the local council Inspector for sign off. No issues reported.
The builder then proceeded to build the front wall and fit the windows. He built a new front wall with a cavity consisting of a 25 mm air gap and 25 mm insulation – this matched the existing stone and block work, where the garage door was previously.
The plasterer who I appointed as Project Manager then plastered all internal walls, he arranged for the electrician to fit the electric sockets as well as a plumber to move pipes as required.
We were advised by both the Builder and the Plasterer there was no need to put any insulation down on the floor other than good underlay and good carpet. We know now this was incorrect advice
The Project Manager did not call out the local council to inspect the work at any of the required stages, nor were any photos taken
At this stage I called the council inspectors in wanting to know whether everything was in order before moving forward with additional internal work
In summary the Inspector advised that
1/ The level of insulation between the internal and external wall should have been 50mm as per the regulations and the builder should have known better
2/ We needed to insulate the floor
3/ We should have appointed an architect and produced detailed plans
I took some advice and then proposed the following to the council in writing
1/ In order to avoid having to take down the wall, would it be possible to install an additional 75mm of Kingspan insulated plasterboard on the internal wall?
2/ We propose to batton most of the floor and install 75mm of insulation on top of the existing concrete. On top of the insulation a visqueen DPC will be installed and then boarded. Because the side door is at the existing floor level then we have proposed to leave the space in front of this this as existing.
I asked the Council to give us an indication as to whether they would accept the above to comply with Building Regulations before we implemented the proposed works – despite several calls, emails and letters the Council are refusing to respond or advise.
When the Council Inspectors visited us they did inform me that they were not an advisory body and we should take advice from our architect – is it really necessary for such a small job to appoint an architect which no doubt would cost up to an additional £1000?
I have since spoken to a couple of local garage conversion specialists both of which were confident they could assist us with the local council however both of these also have been unable to gain a response. Both specialists advised an architect was not really needed
Now 3 months down the line we are stuck – we don’t wish to continue with the work only for the Council to then not to sign it off and then we would have an even bigger issue. Equally we cannot wait forever for the council to advise
Is the architect route really the only option? And would this provide some sort of guarantee? Can anyone advise best way forward?
Thanks
We are currently experiencing problems with our attached garage conversion into a habitable room which have been on-going now for 3 months
We were advised that a Building Regulations application would be the best way to go and we submitted an application to the Local Council.
The application was accepted and a payment was made to the local council and work commenced
At the front of the house the garage door was removed and the builder dug out the foundations and called the local council Inspector for sign off. No issues reported.
The builder then proceeded to build the front wall and fit the windows. He built a new front wall with a cavity consisting of a 25 mm air gap and 25 mm insulation – this matched the existing stone and block work, where the garage door was previously.
The plasterer who I appointed as Project Manager then plastered all internal walls, he arranged for the electrician to fit the electric sockets as well as a plumber to move pipes as required.
We were advised by both the Builder and the Plasterer there was no need to put any insulation down on the floor other than good underlay and good carpet. We know now this was incorrect advice
The Project Manager did not call out the local council to inspect the work at any of the required stages, nor were any photos taken
At this stage I called the council inspectors in wanting to know whether everything was in order before moving forward with additional internal work
In summary the Inspector advised that
1/ The level of insulation between the internal and external wall should have been 50mm as per the regulations and the builder should have known better
2/ We needed to insulate the floor
3/ We should have appointed an architect and produced detailed plans
I took some advice and then proposed the following to the council in writing
1/ In order to avoid having to take down the wall, would it be possible to install an additional 75mm of Kingspan insulated plasterboard on the internal wall?
2/ We propose to batton most of the floor and install 75mm of insulation on top of the existing concrete. On top of the insulation a visqueen DPC will be installed and then boarded. Because the side door is at the existing floor level then we have proposed to leave the space in front of this this as existing.
I asked the Council to give us an indication as to whether they would accept the above to comply with Building Regulations before we implemented the proposed works – despite several calls, emails and letters the Council are refusing to respond or advise.
When the Council Inspectors visited us they did inform me that they were not an advisory body and we should take advice from our architect – is it really necessary for such a small job to appoint an architect which no doubt would cost up to an additional £1000?
I have since spoken to a couple of local garage conversion specialists both of which were confident they could assist us with the local council however both of these also have been unable to gain a response. Both specialists advised an architect was not really needed
Now 3 months down the line we are stuck – we don’t wish to continue with the work only for the Council to then not to sign it off and then we would have an even bigger issue. Equally we cannot wait forever for the council to advise
Is the architect route really the only option? And would this provide some sort of guarantee? Can anyone advise best way forward?
Thanks
Last edited: