I have got a public sewer 3m away in my back garden. So my extension is 2.9m.
Building Control approved my foundations and a 50mm clay master sheet was inserted between the sewer and concrete.
Just heard from the water board that they are rejecting the foundation proposal because I need to be 600mm away from the sewer. There are loads of extensions on street.
600mm....my extension will be too small!!! What can be done to get around this problem? Shall I ignore this letter.
Does building control need the consent letter from the water board to give the final thumbs-up?
Building Control approved my foundations and a 50mm clay master sheet was inserted between the sewer and concrete.
Just heard from the water board that they are rejecting the foundation proposal because I need to be 600mm away from the sewer. There are loads of extensions on street.
600mm....my extension will be too small!!! What can be done to get around this problem? Shall I ignore this letter.
Does building control need the consent letter from the water board to give the final thumbs-up?