As the title says really; How long does concrete need to dry before I can lay tiles on it? The concrete and screed together are 150mm - it was laid 8 weeks ago.
blimey lot off variation like the weather i supposeRules of thumb are:
1) I day per mm
2) 1 week per cm
3) 1 month per inch
Take your pick or get it accurately measured for your circumstances. If you do a search on this forum you will get the correct humidity figutres.
So it looks as though I'll be enjoying concrete floors til xmas then!